Before TSMC’s investor conference on January 13, equipment vendors expected TSMC to raise its capital spending in 2022 based on the company’s multiple investment plan announced in the second half of 2021. TSMC reported $30 billion of capital spending in 2021, about two times larger than Intel’s from the WFE (front-end wafer equipment) perspective. Based on the new guidance, it would spend $40-44 billion in 2022, which is above the industry forecasts.
In our view, TSMC’s higher capital spending implies the company’s more aggressive capacity build-up plan for (1) 3nm and 2nm nodes, as they might see greater demand from Apple and Intel beyond 2023, in addition to the CPU/GPU growth from data centers (2) 3D packaging, due to more demand from HPC clients (3) Specialty nodes, especially at 28/22nm.
Exhibit 1: TSMC Revenues vs CAPEX Trends 2016-2021
TSMC’s major capital spending items in 2022 include:
Exhibit 2: Capital Intensity Ratio for Logic Semiconductor (Non-Memory) ,, 2010-2024
Overall, the foundry industry is expected to account for 30-35% of the global logic (non-memory) semiconductor wafer production in 2022-2023. TSMC leads here by capturing two-thirds of the foundry market. Therefore, TSMC’s higher spending outlook indicates greater semi industry capex as well in 2022, and likely in 2023, if we also consider moderate expansions from other foundry/IDM players.
We usually use the capital intensity ratio (capex divided by sales) to track the semiconductor industry cycle to find early indications of future market growth. The chart above has two lines – the blue one for the entire logic semi industry (foundry and IDM) and the red one for TSMC and Samsung Foundry, the two major players dominating the capacity in leading-edge nodes. Factoring in TSMC’s new forecast for 2022 and industry outlook from increases in other new fab constructions, the capital intensity ratio would reach 23% in both 2022 and 2023, the highest in the past 20 years.
Since the middle of last year, the supply chain has started to reflect concerns about the oversupply of fab capacities going into 2022, if we only look at the normal product cycles for consumer electronic devices such as smartphones and PCs. TSMC’s big announcement clearly indicates there are more structural growth drivers in semiconductors beyond 2021. Its clients too seem to be more optimistic about the silicon wafer demand amid the mega trend of digital transformation. If we use the capital intensity ratio to forecast the production cycle, it appears we won’t reach the peak before 2024 when most of the new capacities (matured and advanced nodes) start mass production. The current high inventory may only suggest a near-term correction in orders for certain components. 5G applications, HPC and automotive all require more silicon content going forward and will offset the saturated demand in smartphones.
Related Research
Dec 10, 2021
Nov 26, 2024
Sep 28, 2021
Sep 8, 2021
Sep 6, 2021
Dec 16, 2021
Dec 16, 2021
Sep 30, 2021
Jan 20, 2022
Jan 28, 2022
Feb 18, 2022
Apr 29, 2022
May 10, 2022